| name | Maintenance scheduling |
| description | Turn a maintenance backlog into a sequence that fits the production plan. |
| category | operations |
Scheduling maintenance
Every planned job competes with production. Schedule against the plan, not
against the calendar.
Rank by consequence
Statutory and safety-critical inspections first — these have dates, not
priorities. Then by what failure would cost: a single point of failure with no
spare outranks a redundant unit, whatever its due date says.
Fit the window
Match each job's duration and isolation requirement against planned downtime,
changeovers and shift patterns. A four-hour job into a two-hour window becomes
an overrun, which is how planned maintenance loses its slot permanently.
Check before scheduling
Parts in stock or on a confirmed date · the skill available on that shift ·
permits and isolations arranged · whether two jobs need the same isolation and
can be combined.
Flag
Anything overdue against a statutory interval, anything deferred more than
twice, and any asset whose reactive work is outgrowing its planned work.
Never
Schedule without confirming parts, or defer a statutory inspection.