Guides PMs on contemporaneous recordkeeping, delay notices, and documentation practices that support potential construction claims.
用 Codex 或 Claude 帮你安装 复制这段 Prompt,粘贴到 Codex、Claude 或其他助手里,让它检查 Skill 页面并帮你完成安装。
菜单
Guides PMs on contemporaneous recordkeeping, delay notices, and documentation practices that support potential construction claims.
用 Codex 或 Claude 帮你安装 复制这段 Prompt,粘贴到 Codex、Claude 或其他助手里,让它检查 Skill 页面并帮你完成安装。
基于 SOC 职业分类
Building envelope systems including curtain wall, roofing, waterproofing, cladding, and the four control layers for construction managers.
Guides construction PMs through building commissioning, TAB, punch lists, O&M documentation, warranties, and project closeout.
Contract administration guidance for construction PMs—notice requirements, change orders, T&M documentation, claims, liens, and subcontract management.
Guidance for construction PMs on correctional facilities, jails, and detention centers including security systems, codes, and specialized building requirements.
Construction management for museums, cultural centers, galleries, archives, and institutional facilities requiring specialized environmental control and collection protection.
Data center construction guidance for mission-critical facilities including power, cooling, redundancy, and commissioning.
| name | claims-delay-documentation |
| description | Guides PMs on contemporaneous recordkeeping, delay notices, and documentation practices that support potential construction claims. |
Important Disclaimer: This skill provides documentation awareness and guidance only. Actual claims preparation and prosecution should be handled by qualified claims consultants and legal counsel. Project managers focus on building the contemporaneous record; claims professionals use that record to pursue recovery.
| Documentation Type | Purpose | Timing | Reference |
|---|---|---|---|
| Daily Logs | Record events, conditions, workforce, issues | Same day as events occur | Contemporaneous Recordkeeping |
| Delay Notices | Preserve rights, notify owner of impacts | Within contractual timeframes | Delay Notice Templates |
| Photo/Video | Visual evidence of conditions and progress | Continuous throughout project | Contemporaneous Recordkeeping |
| Impact Records | Document productivity losses and disruption | As impacts occur | Disruption Documentation |
| Acceleration Records | Document directed or constructive acceleration | When acceleration begins | Acceleration & Compression |
| Delay Type | Owner Caused | Contractor Caused | Third Party/Force Majeure |
|---|---|---|---|
| Excusable | Yes - time extension warranted | No | Often yes - depends on contract |
| Compensable | Usually yes - time + money | No | Typically no - time only |
| Concurrent | Typically bars both parties from recovery | See Entitlement vs Quantum | Complex analysis required |
| Notice Type | Typical Deadline | Consequence of Late Notice |
|---|---|---|
| Delay Notice | 7-14 days from discovery | May waive claim rights |
| Impact Notice | Varies by contract | Reduced recovery potential |
| Reservation of Rights | Immediately upon concern | Weakened claim position |
| Claim Submission | 21-30 days after impact ends | May bar recovery entirely |
Critical: Always check your specific contract for notice requirements. Deadlines vary significantly.
See Delay Notice Templates for sample language.
| Aspect | Delay | Disruption |
|---|---|---|
| Definition | Extended project duration | Loss of productivity without time extension |
| Impact | Later completion | Higher costs, same duration |
| Documentation | Schedule analysis | Productivity records |
| Recovery | Time extension +/- costs | Additional costs only |
| Analysis Method | CPM schedule analysis | Measured mile, studies |
See Disruption Documentation for detailed guidance.
| Method | Best Used When | Reliability | Reference |
|---|---|---|---|
| Measured Mile | Comparable unimpacted work exists | Highest | Impact Quantification |
| Industry Studies | No project-specific baseline | Moderate | Impact Quantification |
| Modified Total Cost | Some costs segregable | Moderate | Impact Quantification |
| Total Cost | No other method possible | Lowest - disfavored | Impact Quantification |
| Situation | Action | Reference |
|---|---|---|
| Complex delay with multiple causes | Engage scheduling consultant | Expert Report Basics |
| Significant productivity losses | Engage claims consultant | Expert Report Basics |
| Dispute likely to proceed to litigation | Engage early for document strategy | Claim Narrative Structure |
| Acceleration being considered | Consult before agreeing | Acceleration & Compression |
| Component | Purpose | Key Elements |
|---|---|---|
| Entitlement | Prove liability exists | Contract terms, breach, causation |
| Quantum | Prove damage amount | Costs, lost productivity, analysis |
| Narrative | Tell the story clearly | Chronology, facts, exhibits |
See Entitlement vs Quantum and Claim Narrative Structure.
Record Every Day:
See Contemporaneous Recordkeeping for complete guidance.
| Document Category | Retention Period | Storage Requirements |
|---|---|---|
| Daily logs and reports | Project + 10 years minimum | Original format, indexed |
| Photos and videos | Project + 10 years minimum | Organized by date and area |
| Correspondence | Project + 10 years minimum | Complete threads preserved |
| Schedule files | Project + 10 years minimum | Native format (.xer, .mpp) |
| Cost records | Project + 10 years minimum | Auditable detail |
Remember: Document during the project; let claims professionals prosecute later. Your job is to build the record.