- name
- early-phase-enabling-trades
- description
- Sitework, excavation, demolition, environmental abatement, and underground utility guidance for construction PMs and field supervisors.
# Early Phase Enabling Trades
Expert-level guidance for sitework, excavation, demolition, environmental abatement, and underground utilities in commercial/institutional construction. This skill covers the critical first phases of construction that establish the foundation for all subsequent work.
## Quick Reference Tables
### OSHA Excavation Soil Classification
| Type | Description | Max Allowable Slope | Cohesive Strength |
|------|-------------|---------------------|-------------------|
| **Type A** | Clay, silty clay, sandy clay, clay loam (ceite) | 3/4H:1V (53°) | 1.5 tsf or greater |
| **Type B** | Angular gravel, silt, silt loam, sandy loam, previously disturbed soils | 1H:1V (45°) | 0.5-1.5 tsf |
| **Type C** | Gravel, sand, loamy sand, submerged soil, unstable rock | 1.5H:1V (34°) | Less than 0.5 tsf |
> **Reference:** [Trench Safety & OSHA Requirements](references/trench-safety-osha.md)
### Soil Classification Quick Reference (USCS)
| Symbol | Description | Characteristics |
|--------|-------------|-----------------|
| **GW** | Well-graded gravel | Excellent drainage, high bearing |
| **GP** | Poorly-graded gravel | Good drainage, moderate bearing |
| **SW** | Well-graded sand | Good drainage, good bearing |
| **SP** | Poorly-graded sand | Good drainage, lower bearing |
| **SM** | Silty sand | Fair drainage, fair bearing |
| **SC** | Clayey sand | Poor drainage, fair bearing |
| **ML** | Silt | Poor drainage, low bearing |
| **CL** | Lean clay | Poor drainage, fair bearing |
| **CH** | Fat clay | Very poor drainage, variable bearing, expansive |
| **OH/OL** | Organic soils | Not suitable for structural support |
> **Reference:** [Geotechnical Fundamentals](references/geotechnical-fundamentals.md)
### Compaction Requirements by Application
| Application | Minimum % Compaction | Test Method | Lift Thickness |
|-------------|---------------------|-------------|----------------|
| Structural fill under footings | 95-98% Modified Proctor | Nuclear density | 6-8" loose |
| Building pad/slab subgrade | 95% Modified Proctor | Nuclear density | 8" loose |
| Utility trench backfill (pipe zone) | 95% Standard Proctor | Nuclear density | 6" loose |
| Utility trench backfill (above pipe) | 90-95% Standard Proctor | Nuclear density | 8-12" loose |
| Pavement subgrade | 95% Modified Proctor | Nuclear density | 8" loose |
| General site fill | 90% Standard Proctor | Nuclear density | 12" loose |
> **Reference:** [Excavation & Earthwork](references/excavation-earthwork.md)
### Shrink and Swell Factors
| Material | Shrink Factor | Swell Factor | Bank to Compacted |
|----------|---------------|--------------|-------------------|
| Clay | 0.90 | 1.30 | 0.90 |
| Common earth | 0.90 | 1.25 | 0.90 |
| Gravel | 0.92 | 1.12 | 1.05 |
| Sand | 0.95 | 1.12 | 0.95 |
| Rock (blasted) | 0.67 | 1.50 | Variable |
> **Reference:** [Excavation & Earthwork](references/excavation-earthwork.md)
### Underground Utility Pipe Materials
| Application | Common Materials | Typical Sizes | Key Considerations |
|-------------|-----------------|---------------|-------------------|
| Sanitary sewer | PVC (SDR 35), DIP, VCP | 4"-36" | SDR 35 to 15' depth; DIP for deeper |
| Storm drainage | RCP, HDPE, PVC, CMP | 12"-96" | RCP for heavy loads; HDPE for flexibility |
| Domestic water | DIP, PVC (C900), HDPE | 4"-16" | DIP most common; HDPE for HDD |
| Fire water | DIP, cement-lined | 6"-12" | Typically ductile iron |
| Gas (distribution) | PE, steel | 2"-6" | Yellow PE most common |
| Electrical duct | PVC (Sch 40/80), HDPE | 2"-6" | Concrete encased in traffic areas |
> **Reference:** [Sanitary & Storm](references/underground-utilities-sanitary-storm.md) | [Water & Fire](references/underground-utilities-water-fire.md) | [Dry Utilities](references/underground-utilities-dry.md)
### Dewatering System Selection
| Groundwater Condition | Soil Type | Recommended System | Typical Depth |
|----------------------|-----------|-------------------|---------------|
| Low volume, shallow | Any | Open sumps | 0-6' |
| Moderate volume | Sand, gravel | Wellpoints | 0-18' |
| High volume, deep | Sand, gravel | Deep wells | 15-100'+ |
| Fine soils, low perm | Silt, fine sand | Eductors | 0-60' |
| Contaminated | Any | Contained system | Varies |
> **Reference:** [Dewatering Systems](references/dewatering-systems.md)
### Shoring System Selection
| Excavation Depth | Soil Conditions | Typical System | Design Responsibility |
|------------------|-----------------|----------------|----------------------|
| <5' | Type A soil | Open cut or box | Contractor |
| 5-12' | Type B/C soil | Trench box/shield | Contractor |
| 5-20' | Mixed conditions | Sheet piling | Engineer required |
| 10-40' | Tight site, adjacent structures | Soldier pile & lagging | Engineer required |
| 20'+ | High groundwater | Secant/tangent piles | Engineer required |
| Variable | Permanent installation | Soil nail wall | Engineer required |
> **Reference:** [Shoring & Excavation Support](references/shoring-excavation-support.md)
### APWA Utility Color Codes
| Color | Utility Type | Examples |
|-------|-------------|----------|
| **Red** | Electric | Power lines, conduit, lighting |
| **Yellow** | Gas/Oil/Steam | Natural gas, propane, petroleum |
| **Orange** | Communication | Telephone, cable TV, fiber optic |
| **Blue** | Water | Potable water, irrigation |
| **Green** | Sewer/Drain | Sanitary sewer, storm drain |
| **Purple** | Reclaimed water | Non-potable water |
| **Pink** | Temporary survey | Survey marks, proposed excavation |
| **White** | Proposed excavation | Dig area boundary |
> **Reference:** [Utility Coordination & Locates](references/utility-coordination-locates.md)
### Asbestos-Containing Materials (Common Locations)
| Material | Friability | Typical Location | Removal Method |
|----------|------------|-----------------|----------------|
| Pipe insulation | Friable | Mechanical rooms, ceilings | Full containment |
| Spray-on fireproofing | Friable | Structural steel, decking | Full containment |
| Acoustic ceiling tile | Non-friable | Ceilings throughout | Wet removal |
| Floor tile (9x9, 12x12 VAT) | Non-friable | Throughout building | Wet removal |
| Mastic/adhesive | Non-friable | Under flooring | Leave in place or removal |
| Transite siding/panels | Non-friable | Exterior, mechanical rooms | Wet, intact removal |
| Roofing felts | Non-friable | Roof systems | Wet removal |
| Joint compound | Friable | Drywall joints | Full containment |
| Boiler insulation | Friable | Mechanical rooms | Full containment |
> **Reference:** [Asbestos Abatement](references/asbestos-abatement.md)
### Environmental Regulatory Framework
| Regulation | Agency | Applies To | Key Requirements |
|------------|--------|-----------|------------------|
| NESHAP | EPA | Asbestos | 10-day notification, work practices |
| OSHA 1926.1101 | OSHA | Asbestos (construction) | Worker protection, exposure limits |
| OSHA 1926.62 | OSHA | Lead (construction) | Worker protection, medical monitoring |
| RRP Rule | EPA | Lead paint renovation | Certified renovators, work practices |
| TSCA | EPA | PCBs | Disposal requirements |
| RCRA | EPA | Hazardous waste | Manifests, disposal |
| NPDES | EPA/State | Stormwater | SWPPP, inspections, BMPs |
> **Reference:** [Lead & Hazmat Abatement](references/lead-hazmat-abatement.md) | [Permits & Regulatory](references/permits-regulatory.md)
### Pipe Testing Requirements
| Pipe Type | Test Method | Test Pressure/Duration | Acceptance Criteria |
|-----------|-------------|----------------------|---------------------|
| Sanitary PVC | Low-pressure air | 4.0 psi, 2 min minimum | No audible leaks |
| Sanitary PVC | Mandrel (deflection) | 5% of ID | Pass without force |
| Storm RCP | Exfiltration | 2' head above GW | <200 gal/inch-dia/mile/day |
| Water main DIP | Hydrostatic | 150% working, 2 hrs | Max allowable leakage per AWWA |
| Water main PVC | Hydrostatic | 150% working, 2 hrs | Max allowable leakage per AWWA |
| Gas PE | Pressure test | 1.5x MAOP, 1 hr | No pressure drop |
| Electrical duct | Mandrel | Per spec | Full pass-through |
> **Reference:** [Testing & Inspections](references/testing-inspections.md)
### Erosion & Sediment Control BMPs
| BMP Type | Application | Maintenance Frequency | Key Installation Requirements |
|----------|-------------|----------------------|------------------------------|
| Silt fence | Perimeter, slope bases | Weekly + after 0.5"+ rain | Trenched 6"+, posts 6' OC |
| Inlet protection | Storm inlets | Weekly + after rain | Filter fabric or gravel |
| Stabilized entrance | Site access points | Daily, add stone as needed | 50' min length, 6" stone |
| Sediment basin | Large disturbed areas | After each storm event | Per SWPPP sizing |
| Erosion blanket | Slopes >3:1 | Inspect weekly | Stapled per manufacturer |
| Concrete washout | Mixer/pump cleaning | Weekly, dispose properly | Lined pit, 10' from drainage |
> **Reference:** [Erosion & Sediment Control](references/erosion-sediment-control.md)
### Survey Layout Tolerances
| Element | Horizontal Tolerance | Vertical Tolerance | Verification Method |
在 GitHub 查看